Estimated Project Development Time
Oct 2016
Bird Studies begin
Jun 2019
Environmental Impact Assessment baseline studies begin.
Sep 2019
Noise Monitoring begins
Nov 2019
Community and Engagement process begins
Mar 2020
Site investigations commence
May 2020
Layout developed for Environmental Assessment and Community Engagement
Jan 2021
Planning Application submitted to An Bord Pleanála on 28th January 2021.
Aug 2021
Request for Further Information (RFI) received from An Bord Pleanála.
Nov 2021
Request for Further Information (RFI) submitted to An Bord Pleanála.